Entergy Wins OK for $870m Power Plant

The Louisiana Public Service Commission voted in late June to approve construction of the Lake Charles Power Station, a 994 megawatt combined-cycle power plant.

Entergy Louisiana says it expects to issue full notice to proceed to construction by Aug. 1.

The plant is scheduled to be in service by June 2020. The company says it will cost around $872 million to build including transmission and other project-related costs and contingency.

The plant will employ around 30 people once complete.

To contact the author of this article, email david.wagman@ieeeglobalspec.com


Entergy Wins OK for $870m Power Plant

Author : Internet   From : globalspec   Release times : 2018.03.18   Views : 1400

The Louisiana Public Service Commission voted in late June to approve construction of the Lake Charles Power Station, a 994 megawatt combined-cycle power plant.

Entergy Louisiana says it expects to issue full notice to proceed to construction by Aug. 1.

The plant is scheduled to be in service by June 2020. The company says it will cost around $872 million to build including transmission and other project-related costs and contingency.

The plant will employ around 30 people once complete.

To contact the author of this article, email david.wagman@ieeeglobalspec.com


Disclaimers statement: All news (Except for TBB news) are collected from internet,and all copyright reserved by original authors.If they relate to your copyright,please contact us and we will delete in time,thanks.

'
Copyright © 2000-2022 TBB Bearing Provision. All Rights Reserved.
Online Service
TRACY-TBB
MAGGIE-TBB
CHERRY-TBB
YORI-TBB
Asking for price
Asking for price
Release Your Inquiry for FREE !